Sunshine Silver advances mine readiness, targets feasibility Q2 2027 and production in late 2028
קריאה של פחות מדקה
Sunshine Silver reported substantial progress on underground development, infrastructure upgrades and site preparation as it targets a feasibility study in Q2 2027 and return to production in late 2028.
Key Highlights:
- Advanced ~1,200m underground development in H1 2026 and expects ~1,300m more in H2; remaining 2026 work to finish by year-end.
- Completed ~47,600m of a 50,000m infill drilling program as of Sept 30, 2026; additional drill results expected before year-end.
- Initiated Silver Summit multiphase hoist and shaft upgrades; new production hoist commissioned at Jewell Shaft in May 2026.
- Installed ~1,200m of new underground rail with ~1,900m more planned by year-end to improve logistics and safety.
- Legacy mill demolition underway (since 2025) to complete by year-end, preparing site for a new processing facility sized for ~1,000 tpd, upgradable to ~2,000 tpd.