COMMENT: Africa’s missing highways are holding back trade

Thời gian đọc: 11 phút

Africa needs tens of thousands of kilometres of reliable highways to connect its markets. Roads carry 80% of the continent’s goods and 90% of its passenger traffic. Yet only around 30% of Africa’s 1.6mn km of roads outside residential areas are paved.

Nearly half the paved network is concentrated in Algeria, Egypt and South Africa. In low-income African countries, only around 13% of roads are paved. A 2024 World Bank study mapped 315,000km of roads linking 447 African cities and 52 international ports. It identified a further 104,000km of potential links that could shorten journeys between those markets.

Building and maintaining Africa’s roads will require around $50bn a year to 2040, nearly a third of the continent’s estimated infrastructure investment needs, according to the African Union and the OECD. Funding falls short across infrastructure more broadly. In November 2025, the African Development Bank (AfDB) estimated that Africa spends about $75bn a year across all infrastructure, including transport, power and water, against annual needs of $150bn.

The African Continental Free Trade Area (AfCFTA), which began trading in 2021, aims to remove most tariffs on goods traded among its 54 signatory states. The World Bank estimated that full implementation could raise exports between African countries by 81% and lift regional income by around $450bn by 2035. How much of that potential is realised will depend significantly on how quickly and cheaply goods can move between African markets.

The first phase of the Programme for Infrastructure Development in Africa (PIDA), the African Union’s continental plan, helped develop more than 16,000km of roads between 2012 and 2020. By 2025, only 18% of the projects targeted in that phase were operational. In October 2026, the African Union launched a mid-term review of the 69-project second phase to examine delays and recommend which projects to accelerate or restructure. “This Mid-Term Review must go beyond measuring progress: it must explain why projects are delayed,” said Kamugisha Kazaura, the AU Commission’s director for infrastructure and energy.

National highways move first

Nigeria, Kenya and Zambia are now building some of the continent’s largest highways, using financing from international bank syndicates and domestic pension funds, as well as concessions led by Chinese companies. Meanwhile, five West African governments are seeking funding to start work on the 1,028km Abidjan–Lagos coastal motorway.

Planned length and status of selected African highway projects. Sources: governments, contractors, AfDB, ECOWAS, media reports.

Nigeria’s 700km Lagos–Calabar coastal highway would improve road access between ports and commercial centres along the country’s southern coast. President Bola Tinubu commissioned the first 30km in May 2025, and the government temporarily opened it to traffic that December. The stretch forms part of the 47.5km first section from Victoria Island to Eleko. The second section extends another 55.7km to Ode-Omi. Work is also under way further east, in Akwa Ibom and Cross River states.

The 1,000km Sokoto–Badagry superhighway would give Nigeria’s north-west a more direct route to coastal markets in the south-west. It would run from Illela, on the border with Niger, to Badagry, near the border with Benin.

Hitech, the contractor, has reported earthworks and concrete paving on sections in Sokoto and Kebbi and around Badagry. In April 2026, Nigeria’s parliament approved a $516mn loan request to help finance around 120km of the route.

Kenya’s 233km Rironi–Mau Summit project is widening roads on the Northern Corridor, which carries freight from the port of Mombasa through Nairobi towards Uganda. Kenya launched the KSh184bn ($1.42bn) upgrade in November 2025. The two concessions cover work on the main highway through Naivasha and Nakuru and on the parallel road through Mai Mahiu. In November 2026, Kenya’s transport minister said some stretches had received their first layer of asphalt and would reopen temporarily while contractors finished the work.

Zambia is turning 327km of road between Lusaka and Ndola into a dual carriageway under a concession. The road serves the Copperbelt and carries freight towards the DRC. The project also includes bypasses at Kabwe and Kapiri Mposhi and the rehabilitation of a 45km link towards Luanshya. The main carriageway was 78% complete in June 2026, according to Zambia’s Road Development Agency.

Morocco is building the 60km inland Rabat–Casablanca motorway to ease congestion on existing routes. The project is estimated to cost 6.5bn dirhams ($663mn). By mid-October 2026, work was under way on the piers of the 840-metre El Maleh viaduct.

In South Africa, the national roads agency values its N2 and N3 upgrades in KwaZulu-Natal at around R52bn ($3.2bn). The N3 carries freight inland from Durban.

From Chinese loans to pension funds

Chinese policy banks helped finance an earlier generation of African highways. Chinese loan commitments to African governments and regional institutions exceeded $10bn every year from 2012 to 2018. They fell from $3.9bn in 2023 to just under $2.1bn in 2024, the latest year covered by Boston University’s Chinese Loans to Africa Database. The 2024 total covered six projects across all sectors, including $1.45bn committed to Angola for roads and electricity transmission.

Uganda’s Kampala–Entebbe expressway, which opened in June 2018, was financed with public funds and a loan from China Exim Bank, a Chinese state-owned policy bank. China Communications Construction Company (CCCC), a Chinese state-owned infrastructure contractor, built it under a contract originally valued at $476mn. Uganda registered the proposed 95km Kampala–Jinja expressway as a public-private partnership in 2017. Its works ministry was still advertising for advisers to the $1.5bn project in 2026.

Chinese contractors are also building highways backed by African pension funds. China Road and Bridge Corporation, a subsidiary of CCCC, is working with Kenya’s National Social Security Fund, a statutory pension fund, on one of the two concessions. Shandong Hi-Speed Road and Bridge International, another Chinese infrastructure contractor, holds the other.

The new concessions rely on tolls paid by drivers. Kenya cancelled the previous Vinci-led concession in 2025. That deal would have required government payments of around KSh23bn ($177mn) a year, according to local media reports citing Treasury disclosures. The reported terms for the new deal give the state 60% of toll revenue collected once investors’ return on equity exceeds 16%. Kenya’s Treasury says the terms will save the government KSh76.2bn. In November 2026, Treasury Cabinet Secretary John Mbadi rejected opposition claims that the project’s cost had been inflated. “The design of the road changed from what we initially had,” he said. The opposition Democracy for Citizens Party (DCP) wants the government to drop plans to toll the road.

In Zambia, Macro Ocean Investment Consortium, a Chinese-led group, holds the Lusaka–Ndola concession. Construction began in May 2024. Zambia’s National Pension Scheme Authority (NAPSA), which administers the country’s statutory pension scheme, signed a financing agreement in March 2024 for $300mn of the project’s $650mn financing package. The loan carries interest of 9.5% a year over 13 years, with a three-year construction moratorium followed by ten years of repayments. NAPSA has first claim on repayment from an escrow account funded by designated tolls and other revenues. In June 2026, it said it had received $5.9mn in interest.

Nigeria turned to international bank syndicates for Lagos–Calabar, securing $1.873bn in 2025 for the first 103km. Deutsche Bank led the $747mn first facility. First Abu Dhabi Bank and Afreximbank underwrote the $1.126bn second facility. Both facilities received partial risk cover from the Islamic Corporation for the Insurance of Investment and Export Credit (ICIEC). The policy backing First Abu Dhabi Bank covers Nigeria’s failure to honour its sovereign financial obligations. For the wider highway, the federal government plans to contribute 30% and expects lenders to provide 70%, according to David Umahi, the works minister.

Financing infrastructure in Africa remains expensive despite relatively low reported default rates. The African Union and the OECD put the default rate on infrastructure debt at below 2% in Africa, compared with nearly 5% in Asia and 10% in Latin America. They estimate that infrastructure projects in Africa need to earn around 13% on average to cover borrowing costs and the returns shareholders expect, compared with 8% in OECD countries. Afreximbank says its Africa Infrastructure Financing Facility, launched in February 2026, is designed to address another constraint: “the gap between political approval and financial execution”.

Infrastructure debt default rates and required project returns. Source: African Union, OECD.

On cross-border highways, toll forecasts also depend on when neighbouring countries open their sections and how quickly trucks clear the border.

The missing links

The idea of a continental network goes back to the early 1970s. The 6,260km Lagos–Mombasa highway, as measured by the African Union, would link the Atlantic and Indian Ocean coasts as part of the Trans-African Highway network. More than five decades later, its sections in Kenya and Uganda are paved, but a long gap remains across the DRC, where much of the route is still earth track that becomes impassable in heavy rain.

Work is under way at the eastern edge of that gap. Uganda and the DRC are upgrading 223km of roads in eastern DRC, including the 80km Kasindi–Beni road, which was around 61% complete in March 2026, the 54km Beni–Butembo road, which was around 5% complete, and the 89km Bunagana–Rutshuru–Goma road. Dott Services, the Ugandan contractor, is supposed to provide 60% of the cost and each government 20%. Closing the rest of the gap would require separate agreements and financing.

A route from West Africa to southern Africa would use parts of several corridors, including the 9,610km Tripoli–Windhoek–Cape Town highway. One missing link lies between the Central African Republic and the Republic of the Congo, where the proposed alignment crosses rainforest in the Sangha Basin.

In October 2026, the AfDB published a biodiversity plan for paving around 47km between Ouesso and Pokola in the Republic of the Congo and building a 616-metre bridge over the Sangha River. Further south, INZAG, a German contractor, lists the rehabilitation of 146km of road between Caiundo and Savate in Angola for 2026–28.

Mining traffic gives parts of the route between Angola and the Copperbelt a clearer commercial case. In August 2026, the AfDB Group approved a $255mn loan and a $10mn grant for Zambia’s part of the Lobito Corridor. The package supports a primarily rail-led project that also includes upgrading 105km of the Mwinilunga–Jimbe road towards the Angolan border.

The Cairo–Cape Town route runs around 8,860km via Gaborone. The African Development Fund (ADF), the AfDB’s concessional lending arm, has financed work on the Mombasa–Nairobi–Addis Ababa corridor, including the 122km Turbi–Moyale section in Kenya. Further north, Egypt suspended Sudan-bound truck crossings at Qustul on October 15, 2026, after two Egyptian drivers were shot dead in Khartoum, according to media reports. A restriction at one crossing can interrupt through freight even where countries have already paid for the road.

Abidjan–Lagos looks for money

On October 30, 2026, ministers from Côte d’Ivoire, Ghana, Togo, Benin and Nigeria met in Lomé to review progress on the Abidjan–Lagos motorway. The six-lane highway is estimated to cost $14.7bn. Feasibility studies and preliminary designs are complete, and the project has moved to the investment stage. The studies divided the route into 15 proposed concession packages, with financing options still being worked out.

At the meeting, Togo said options under review could bring the cost down to $13bn, or to $10bn in some scenarios. It also proposed sharing financing costs across the five countries so that those with less profitable sections would not have to fund them alone. Togo also called for land along the route to be cleared through a single, centrally coordinated process rather than separate national procedures.

The AfDB, the lead arranger, has provided more than $25mn for studies and technical assistance. It is seeking around $500mn in low-cost development finance for the initial works to help attract private investment. The five countries have set up a joint authority to oversee the highway’s design, construction and operation. Land and financing for the first sections still need to be secured.

Late payments and broken contracts

The AfDB’s approach on Abidjan–Lagos is to use low-cost development finance for the early works to draw in private investors. Under that model, private operators would take toll concessions on the busiest sections, while governments make availability payments on stretches where tolls would not cover the cost.

Once contracts are awarded, late payments can slow construction. Kenya borrowed against future fuel levy receipts to clear arrears and get contractors back to work. Unpaid bills to road contractors fell by around a quarter in the year to June 2026 but still stood at KSh98.17bn ($756mn).

Libya’s planned 1,750km coastal motorway faces both a payment delay and a terminated contract. Italy pledged $5bn for infrastructure under a 2008 treaty that included the motorway. At the western end, contractor Todini Costruzioni Generali was still waiting for an advance payment from Italy in November 2026, the Tripoli-based highway authority said.

On the eastern sector, which was originally around 400km long, Italian contractor Webuild sought to raise the contract value from around €940mn ($1.05bn) to nearly €2.4bn ($2.69bn), citing higher construction costs, according to media reports. In October 2026, authorities in eastern Libya terminated the contract and sought to enforce Webuild’s performance bond. Webuild has challenged the move in a court in Turin. A Libyan delegation was expected in Rome in November to discuss redesigning parts of the route and dividing it into smaller lots.

Insecurity, skills and upkeep

Insecurity threatens road construction in Nigeria and the DRC. In October 2026, gunmen killed two security officers and a foreign worker at a Sokoto–Badagry construction site in Kebbi state, north-western Nigeria. The attackers had crossed from neighbouring Sokoto state, according to local media reports.

Kebbi state had donated ten vehicles to security forces guarding the route in December 2025. “No meaningful development can thrive without security,” said Nasir Idris, the state governor. In the eastern DRC, Dott Services cited insecurity among the constraints on work on the Kasindi–Beni–Butembo road project.

A shortage of specialist skills is another obstacle to building highways. Demand for construction project professionals in sub-Saharan Africa is projected to rise from around 260,000 in 2025 to more than 410,000 by 2035, according to the Project Management Institute.

In South Africa, the national roads agency linked delays on the Msikaba bridge to difficulties fabricating steel deck segments for its 580-metre main span. Costs for the bridge and associated roads rose from R1.6bn ($97mn) to R2.2bn ($133mn), and completion has slipped to 2029 from March 2025, according to local media reports.

Maintaining roads once they open is another constraint. Maintenance ranked lowest among the infrastructure governance categories assessed across 31 African countries, according to the African Union Commission and the OECD. South Africa has budgeted R63.9bn ($3.9bn) for its national non-toll network over the three years to 2028/29. Its roads agency plans to resurface 6,000km across the national network over that period.

Roads into the forest

The environmental cost of completing the highways between West and East Africa could be high. The missing links on the Lagos–Mombasa route run through the Congo Basin, where new construction could destroy and fragment large areas of natural habitat. The damage could extend well beyond the carriageway.

Once trucks can reach remote areas year-round, farms and settlements can spread along the roadside and new tracks can open up more forest. A study published in Global Environmental Change in July 2026 found that nearly 94% of the forest loss it mapped in the Congo Basin between 2001 and 2021 occurred within 4km of a settlement.

In the Republic of the Congo, a World Bank study identified Sangha and Likouala as particularly vulnerable to deforestation. The AfDB’s biodiversity plan for the Ouesso–Pokola road covers both areas. Choosing a route that avoids intact forest can limit the land cleared for construction. Controlling access to side roads can help limit the clearing that follows.

Building the roads also produces emissions. Nigeria’s 2024 draft environmental assessment estimated around 85,900 tonnes of carbon dioxide equivalent for the first 47.5km of Lagos–Calabar, mainly from machinery.

Time saved at the border

The value of these highways to traders depends on how much time they save trucks over the whole journey. In the DRC, the AfDB wants to cut truck journey times on the Mbuji-Mayi–Kananga road from 72 hours to 12. In West Africa, the Abidjan–Lagos motorway is meant to speed up freight along the coast. Its benefits will also depend on how quickly trucks clear customs. At the border between Nigeria and Benin, trucks heading into Benin take nearly 53 hours to cross on average.

Of the projects covered here, the most advanced are national roads with traffic already on them and dedicated financing, such as Lusaka–Ndola, which was 78% complete in June 2026, Rironi–Mau Summit and the first sections of Lagos–Calabar. Financing for the first sections of the cross-border Abidjan–Lagos motorway has yet to be secured.