RWE receives first foundations for next phase of 1.6-GW Nordseecluster
November 24 (Renewables Now) - German energy company RWE AG (ETR:RWE) has received the first 10 foundations for the second phase of its 1.6-GW Nordseecluster offshore wind project in the German North Sea.
The second phase, Nordseecluster B, involves the installation of 60 turbines with a total capacity of 900 MW. These will add to the 660 MW of capacity which is being established as part of the first phase, Nordseecluster A, and is due to be fully operational in early 2027.
The first 10 foundations for Nordseecluster B have arrived and have been successfully unloaded at the Eemshaven port in the Netherlands, RWE said on Monday. Installation of the foundations, which were supplied by Chinese manufacturer Dajin Heavy Industry, is expected to begin in 2027. The deployment of the turbines will follow in 2028. Nordseecluster B is scheduled to start commercial operations in early 2029.
The Nordseecluster project, located around 50 km north of the island of Juist, is one of the largest wind farms currently being built off the German coast. Once completed, the facility will generate around 6.5 TWh of electricity annually.
The power will support RWE’s industrial customers in their decarbonisation efforts. For example, Amazon signed earlier in 2026 a power purchase agreement (PPA) with the German energy group, securing 110 MW from Nordseecluster B.
RWE owns 51% of the Nordseecluster project with the remaining 49% held by its partner, Norges Bank Investment Management. The energy company is responsible for the construction and subsequent operation of the wind farm.
In addition to Nordseecluster, RWE is involved in other large offshore wind projects, including Sofia of 1.4 GW, Vanguard East & West of 2.8 GW, Thor of 1.1 GW and OranjeWind of 795 MW.